Untreated, unscreened wastewater has been discharged into Tarakena Bay. Check LAWA.org.nz before visiting beaches.
Untreated, unscreened wastewater has been discharged into Tarakena Bay. Check LAWA.org.nz before visiting beaches.

Between approximately 8 am on 25 June and 7 am on 26 June, the short outfall pipe discharged untreated wastewater into Tarakena Bay.

Signs are in place along the coastline to alert water users of areas which may be impacted by this event. Water quality samples will be collected from coastal locations once improved weather conditions allow. 

Check LAWA.org.nz before visiting beaches along the south coast. 

Public health information can be found on Health NZ's website

Wellington Water crews responding to wastewater overflow on State Highway 2
Wellington Water crews responding to wastewater overflow on State Highway 2

Our team is responding to a wastewater overflow on State Highway 2 which has stopped this afternoon. The overflow was from a manhole on the southbound lanes close to the Ngauranga exit, discharging into the habour through the stormwater drains.

While the overflow has stopped, our teams are working to clear a blockage which still remains. They are working at pace to identify the blockage and get this cleared. 

One southbound lane clasure remains in place approaching Ngauranga while work is underway.

In this section

Moa Point Road to Recovery

The Recovery Road Map provides an indicative timeline and key milestones to restore the plant back to the way it was prior to the flooding, and address the design flaw identified in the hydraulic report. 

The roadmap identifies key milestones that we’ll report back on regularly, so the community can hold us to account and keep track of our progress on the road to recovery. These dates are all indicative, and we will regularly report on our progress.

We know that every extra day the plant is not fully operational affects the community. Our teams are focused on restoring services as quickly and safely as possible, and we’ll keep the community up to date on our progress. We have built this timeframe to be realistic and achievable – but alongside this, we are doing all we can to accelerate delivery.