Water Networks / Projects / Projects / Kipling Street And Bannister Avenue Wastewater Renewals Project

Kipling Street and Bannister Avenue Wastewater Renewals Project

Overview
Current status
Background
All Updates
Start Date
24/08/2026
End Date
31/03/2027
Contact:

If you have any questions about this work, please contact:

Wellington Water, 04 912 4400

Latest Updates

13/08/26

Our contractors will be starting works from late August.

Kipling Street and Bannister Avenue Wastewater Renewal Project

We're undertaking the renewal of a wastewater pipe that services Kipling Street and Bannister Avenue. The pipe needs to be replaced as it is in poor condition. This upgrade is part of our ongoing commitment to strengthening the wastewater network and minimising the risk of overflows and unplanned maintenance.

Street overview of the works


The first phase of works start in August 2026 in Kipling Street, and include a section of Bannister Avenue and Elliot Street. Phase 2 works are scheduled to start in late November and be completed by February- March 2027.  This involves reconstructing the existing wastewater pipe from 40 Kipling St to 31 Elliot Street. 

If you have any questions about this project please contact:  

Project Engineer: Peter Mumm (E Carson and Sons Ltd) - 027 289 2400

Email peter@ecarson.co.nz or engagement@tiakiwai.co.nz

 

All Updates

13/08/26

Our contractors will be starting works 

From  24 August 2026 to 2 October 2026

-         Work will take place Monday to Friday

-         Working hours are 7:30am to 5:30pm


What to expect

The works will start in Kipling Street, and include a section of Bannister Avenue and Elliot Street. Phase 2 works are scheduled to start in late November and be completed by February- March 2027.  This involves reconstructing the existing wastewater pipe from 40 Kipling St to 31 Elliot Street. 

·         To ensure the safety of residents and contractors, No Parking signs and traffic cones will be installed where required.

·         We will provide at least 24 hours' notice before temporary parking restrictions are put in place.

·         If your vehicle is parked within the work zone, you may be asked to move it.

·         If a vehicle needs to be relocated, the towing operator will move it to the nearest available legal parking space and leave details of its new location.

·         Access to driveways will be maintained throughout the works.

·         If access to your property is temporarily affected, our team will liaise directly with you in advance.

·         Please take care when travelling near the work site and follow all signage and directions from traffic management staff.

We appreciate your patience and understanding while this important work is completed. Our team is dedicated to minimising disruption and completing the project as safely and efficiently as possible.